A Finnish district heating company Elenia Lämpö Oy invested in Savosolar solar thermal system to produce CO2-free energy for their customer, which in this case is a nursing home located in Hämeenlinna. The heat is used for domestic hot water and pool heating.
The installation is the biggest operational solar thermal system in Finland.
Lolland forsyning’s district heating plant in Søllested is located on the island of Lolland and was the first installation, where Savosolar’s double glazed collectors were used. The double glazing reduces heat losses through the glass side of collector and offers a higher efficiency, especially at higher operation temperature levels and during the darker months of the year. Søllested district heating plant has ca. 500 customers and also uses a 5 MW straw boiler and an oil burner to produce its heat.
The collector field in Søllested has a so-called hybrid field, with both single and double glazed collectors. The single glazed collectors are in the cold end of the collector rows and increase the low temperature as rapidly as possible, while the double glazed collectors are located in the warm side of the collector rows where it is more important to reduce the heat losses.
In Søllested, Savosolar was faced with a special challenge since the customer’s land has a sewerage pipe running through it. Since the owner of the sewer pipe needs to be able to access it in case of maintenance, Savosolar supplied a collector field which both optimised the use of the available land, while still providing access to the sewer pipe
Savosolar delivered -once again- the largest solar thermal installation in Finland. This system is located way North in Tupos, Liminka – less than 200 km from the Arctic Circle.
The heating load of Tupos district heating is usually covered by wood pellets. Yet during summer time, the load is often so low, that the substantial wood pellet burner cannot be properly used and an oil burner got used, instead. The special challenge here has been to design a very efficient solar thermal system that could replace the oil consumption in summer to run the district heating network almost completely fossil-free.
UNDER CONSTRUCTION
Bad Rappenau, Germany (largest flat plate collector plant in Germany)
Savosolar has been selected as general contractor to build a +20 MW solar thermal system on behalf of Bauer Holzenergie GmbH for its district heating network, which supplies households and an industrial process for drying fruits with healthy heating. Only about 1,800 pieces of Savo 16S large scale high performance flat plate collectors are sufficient to getting combined with an 8,000 m³ heat storage tank and
provide carbon free heat for the needs of all connected consumers.
Additionally, a PV system will be built on site to generate the electricity consumed by the solar pumps, thus
unburdening the local power grid.